Pembangunan Velodrome Capai 40 Persen
.
photo Reza Hapiz - Beritajakarta.id

Velodrome Construction Has Reached 40 Percent

The Velodrome bike racing construction in Rawamangun, East Jakarta has reached 40 percent. This achievement is faster four percent compared to a plan that has been set.

The construction has been ongoing since June 2016 and will be complete in June 2018

According to Iwan Takwin, Manager of Velodrome Venue Project for PT Jakarta Propertindo (Jakpro), the Velodrome project is using the concept of design and build. 

Sumarsono Optimistic Velodrome Construction Finish On Time

"The construction has been ongoing since June 2016 and will be complete in June 2018," he disclosed, when he accompanied the review conducted by Jakarta Governor, Basuki T. Purnama, Friday (2/24).

His party also has conducted innovations in anticipation of the weather factor. This is because, this month is predicted the peak of the rainy season.

"If the inundation occurs, we'll soon do pumping," he stated.

As known, the Rawamangun Velodrome is one of the venues that will be used in the arena of 2018 Asian Games.

Linked News
Popular News indeks
  1. Commission E Urges Residents to Increase Role in Preventing DHF

    access_time19-12-2024 remove_red_eye1219 personDessy Suciati
  2. Transjakarta Adjusting Service as Simpang Pramuka and Rawamangun Bus Stops Closed

    access_time18-12-2024 remove_red_eye1056 personAldi Geri Lumban Tobing
  3. Transjakarta, Telkomsel to Improve Service for Customers

    access_time19-12-2024 remove_red_eye910 personAldi Geri Lumban Tobing
  4. Acting Governor Monitors Food Stock at Kramat Jati and Cipinang Markets

    access_time19-12-2024 remove_red_eye736 personFolmer
  5. TMII Prepares Stuntman Show to Music Concert

    access_time23-12-2024 remove_red_eye693 personNurito